CAVOREN WPSWelding tools & WPS preparation

Prequalified WPS route checker

Record the main Clause 5 gates and identify known route failures or missing evidence.

View result ↓

Code scope and process

Screen Clause 1.1 scope (including ≥1/8 in [3 mm] and specified minimum yield strength ≤100 ksi [690 MPa]); mark Yes only after checking actual material and design basis.

Clause 5 evidence

Record each member separately; similar strength or a trade name is not a match.

Include CJP/PJP/fillet, backing, root opening, root face, angle, access and backgouging. Tubular requires Clause 10 review.

Do not treat an HSS member alone as proof that Clause 10 applies or does not apply.

RESULTExample
—

Choose the conditions to see the result.

Code screening · verify the complete WPS and project requirements
Need a WPS for a real project?

Share your project details and supporting records. We’ll review the route and scope before preparation.

Order a WPS
Scope & references AWS D1.1 / D1.1M:2025

2025 base edition with July 28, 2026 errata. AMD1 not included.

Guided checklist only; tubular and special contract cases need complete specialist review.

Decision sequence

Check the code scope and loading, process eligibility, each base metal, filler, joint detail, preheat, process table, Table 5.5 variables and special branches.

Result boundary

Clause 5 route screening is not engineering approval, WPS signature, personnel qualification or weld acceptance.