PROJECT INTAKE · FIELD GUIDE

Collect the facts a WPS actually depends on.

This checklist helps a project team assemble the drawing, material, process and contract information needed to prepare a specific welding procedure. It is designed to expose gaps early, while keeping customer facts separate from code conclusions.

Use the checklist in three passes

1

Lock the project basis. Capture the contract’s governing standard and edition, selected unit system, design inputs and required acceptance conditions. Do not silently replace a contract edition with a newer one.

2

Describe the intended production weld. Identify each side of the joint, actual geometry from the drawing, thicknesses, welding position, process sequence, consumables and requested production limits.

3

Attach records with locators. Name each file and relevant page, sheet or detail. Mark unknown items as unknown and identify who can resolve them; a blank is not evidence that a condition is absent.

Route is a conclusion, not an intake field. A project may use the prequalified route when all applicable requirements are met. Where Clause 6 qualification support is needed, an applicable existing PQR may support the WPS. This checklist collects evidence; it does not decide either route automatically.

Project and code basis

Record the contractor/manufacturer and project identifiers, drawing numbers and revisions, code designation and edition stated by the contract, unit system, structural category or loading conditions, and any Engineer or client requirements. Note whether CVN, PWHT, seismic, fatigue, corrosion or other special conditions are specified. Attach the relevant specification or mark the exact document location.

Keep requested conditions distinct from engineering decisions. For example, record “CVN required at −20 °C per project specification section X” with its source.

Joint and base-metal information

  • Identify member 1 and member 2 separately: specification, grade/class, product form and delivery condition.
  • Record actual base-metal thickness on each side and the production thickness range requested.
  • Identify CJP, PJP, fillet, plug or slot weld as applicable; give weld size, effective throat or penetration requirement.
  • Provide drawing/detail ID and revision, joint orientation, groove type and dimensions, root opening/face/radius, backing, backgouging and fit-up tolerances.
  • State plate, pipe or tubular construction; include outside diameter and connection type where relevant.
  • Give intended welding positions and vertical progression where applicable; distinguish production orientation from any test position in qualification records.

A joint callout or a weld symbol alone may not show every dimension needed for a production WPS. Supply a dimensioned detail or approved drawing reference rather than guessing omitted geometry.

Process, consumables and production conditions

For each process segment, state process, operation (manual, semiautomatic, mechanized or automatic), sequence and pass role. Provide filler AWS specification/classification, manufacturer and product, diameter, and the actual gas classification/composition and flow for gas-shielded processes. Include polarity/current type, power-source characteristic, transfer mode, waveform controls, flux and SAW setup when those fields apply.

Provide the parameter source for the intended production settings: client procedure, equipment/product datasheet or other identified basis. Separate root, fill and cap ranges when they differ. Include heat-input limits, preheat/interpass conditions, PWHT, cleaning, consumable storage, weather constraints, tacks and sequence where required by the project or production plan.

When an existing PQR may be needed

Send the full legible qualification record and its supporting test reports, not just an old WPS or an unreadable summary. For every PQR, capture its identifier and revision, manufacturer on record, code edition, test date, test assembly type, weld type, base materials and thicknesses, position/orientation and pipe or tubular diameter where applicable.

Include process-by-process actual values and deposited weld-metal thickness, filler/gas/electrical details, preheat/interpass and PWHT records, and test reports for mechanical tests, NDT and CVN when required. Record page numbers or file locations; mark any missing required test result unresolved.

Gap log and handoff

For every unanswered item, record the missing fact, expected source, resolver and effect on the route. Ask a focused follow-up tied to that gap.

Editable checklist contents

The CSV is a working register with columns for workstream, field, requested information, evidence/source locator, status and follow-up owner. Add rows for multiple joints, materials, process segments and records. It contains no prefilled customer or qualification data.

Download the CSV

Source and limits

Prepared from Cavoren’s AWS D1.1/D1.1M:2025 WPS intake and delivery references, including the Clause 5 and existing-PQR evidence distinctions. The service reference basis records the 2025 base edition and its 2026-07-28 base-edition errata; AMD1 is not included. Contract-specified editions take precedence. This checklist is an original collection aid, not an AWS publication, qualification decision, engineering design review or substitute for the governing standard and project documents.

Convert drawing weld IDs into a WPS coverage register

Start with the drawing revision and weld callout, then collect the detail behind the symbol. Record both materials and thicknesses, weld type and required size, joint geometry, backing/removal, position and access, process, temperatures and special requirements. A weld symbol identifies design intent; it rarely supplies every production variable needed for a WPS. Ask the drawing owner to resolve missing design dimensions rather than choosing them while filling the form.

Register columnWhat it connects
Drawing/revision + weld IDThe exact production location and callout
Material pair, thickness, joint and positionThe target conditions to be covered
WPS number/revision + routeThe proposed controlled production instruction
PQR ID / Clause 5 evidenceThe support reviewed for that weld
Restrictions and unresolved itemsCVN, PWHT, access, geometry or missing facts that prevent issue

Example: a beam, a column and a stiffener do not automatically need three WPSs. They may reference the same supported procedure when their actual conditions fit it. Conversely, two welds on one beam may need different procedures if their process, joint or support differs. The fixed-price offer is one WPS, not an unlimited project package. Use the coverage matrix for supporting PQR checks and keep this weld-to-WPS register linked to the current drawing revision.

Customer facts versus ranges derived during preparation

Customer/project evidencePreparation work using that evidence
Actual drawing, materials/MTR, thickness, position, access and joint dimensionsSelect and check the applicable detail and coverage branch without redesigning the joint
Named consumable/product, gas/flux, equipment mode and usable operating dataMap documented parameters to WPS rows and applicable code limits
Original PQR, pass records and test results where neededDerive only the supported production scope and record its restrictions
Contract CVN/PWHT requirements, customer instructions and real approvalsApply the corresponding additional checks and identify unresolved items

Preparation turns the supplied facts into supported limits and a complete document. Identify who will resolve missing inputs; record the selected option and its source wherever the project allows a choice.

Continue this WPS review

Collect the project facts and source records needed to select a WPS preparation route.