PQR support route checker

Separate Clause 5 eligibility, existing PQR coverage and confirmed need for new qualification testing.

View result ↓

Code scope and process

Screen Clause 1.1 scope (including ≥1/8 in [3 mm] and specified minimum yield strength ≤100 ksi [690 MPa]); mark Yes only after checking actual material and design basis.

Existing qualification

Clause 5 evidence

Record each member separately; similar strength or a trade name is not a match.

Include CJP/PJP/fillet, backing, root opening, root face, angle, access and backgouging. Tubular requires Clause 10 review.

Do not treat an HSS member alone as proof that Clause 10 applies or does not apply.

RESULTExample
—

Choose the conditions to see the result.

Route and variable screening
Need a WPS for a real project?

Share your project details and supporting records. We’ll review the route and scope before preparation.

Order a WPS
Scope & references AWS D1.1 / D1.1M:2025

2025 base edition with July 28, 2026 errata. AMD1 not included.

Organizes route selection from the project conditions and existing-record checks you enter.

Route logic

If all applicable Clause 5 checks pass, Clause 6 WPS procedure tests are exempt. Otherwise inspect valid PQRs and their scope before concluding tests are needed.

CVN

When the contract requires CVN testing, assess supplemental Table 6.8 variables in addition to Table 6.6.

Continue this WPS review

Use known project and record facts to organize route review, then resolve any missing evidence.