CAVOREN WPSAWS D1.1 WPS preparation

Material decisions · AWS D1.1 Clause 5

Base-metal guides for AWS D1.1 WPS decisions

A material entry is one input to a WPS decision. Start with the exact ASTM specification and grade, then check its Table 5.6 strength group, the separate Table 5.11 preheat category, and every remaining Clause 5 condition.

These guides use AWS D1.1/D1.1M:2025 base edition plus the registered July 28, 2026 base-edition errata; AMD1 is not included. The project contract's required edition governs. A listed base metal does not, by itself, establish that a production WPS is prequalified.

Choose the material decision

MaterialDecision this guide answersOpen guide
ASTM A36When does the Table 5.6 Group I thickness limit matter, and when does Group II apply?A36 material groups and thickness
ASTM A572 Grade 50How does Grade 50 differ from A572 Grade 60/65 in filler grouping and preheat category?A572 Grade 50 vs higher grades
ASTM A992What does the Table 5.6 Group II listing establish, and what remains to be checked?A992 and Group II
ASTM A500 Grade B/C HSSHow do the material-group and process-based preheat entries relate to a real tubular joint?A500 HSS and tubular connection decisions
ASTM A588Which plate and shape products are listed in Group II, and when does weathering filler matching apply?A588 product form and weathering filler
Dissimilar base metalsHow should two listed materials in different Table 5.6 groups be handled for filler matching?Dissimilar-material filler matching
Unlisted or unidentified steelWhat records and qualification path are needed when a member cannot be mapped to Table 5.6?Unlisted-steel evidence path

Continue with the linked checks

Use tools to inspect a known branch or value, then review the complete project conditions. A tool result is not a WPS approval or a substitute for the governing code and contract.

What a grade lookup cannot decide

Clause 5 eligibility depends on the complete applicable procedure: both base metals and their combination; process and sequence; filler classification; joint detail and backing; position; member thickness; gas or flux where applicable; preheat and interpass control; and project requirements. Verify material identity against the actual material documentation. A trade name or strength value is not a substitute for the listed specification and grade.

For projects relying on qualification, an existing PQR must be checked against its real records and the applicable qualification provisions. A base-metal group is not a PQR coverage result.

Code references

The material-group decisions summarized here are from AWS D1.1/D1.1M:2025 Table 5.6. Preheat categories are separately listed in Table 5.11. Filler matching is addressed in Table 5.7, and the applicable Clause 5 requirements extend beyond material listing. See the edition and errata basis for scope.