Clause 5 · Service route
AWS D1.1 prequalified WPS preparation
A complete English production WPS prepared for the project conditions you provide, when all applicable prequalified requirements and contract limits can be met.
What this route covers
Prequalified status is determined from the whole WPS and its intended application. The procedure is prepared only after the applicable code edition, contract conditions and target weld are identified.
- Applicable base-metal specifications, grades and thickness conditions for both sides of the joint.
- Permitted process and process sequence. Clause 5 includes SMAW, SAW, GMAW other than short-circuit GMAW (GMAW-S), and FCAW when the applicable requirements are met.
- Joint type and detail, position, geometry, backing or backgouging conditions, and the relevant size or thickness limits.
- Filler-metal classification and actual product, shielding gas or flux where applicable, and compatible operating information.
- Minimum preheat, interpass limits, and any applicable PWHT, CVN, heat-input or project restrictions.
Project information to provide
Send the records that identify the actual weld and its required production conditions. Identify any fields still to be confirmed.
| Information | Useful source | Why it matters |
|---|---|---|
| Governing code and edition; contract notes and unit system | Project specification, purchase order, drawings | The contract edition takes precedence over a default preparation basis. |
| Both base metals, exact grade and product form, thickness | Material certificates, drawings, weld map | Material matching and applicable ranges depend on the actual designation and conditions. |
| Weld identification, CJP/PJP/fillet/plug/slot, detail and position | Drawing, weld symbol, joint detail, fabrication requirements | Geometry and coverage cannot be inferred from a weld label alone. |
| Process by pass or segment, filler product/classification and diameter | Approved shop practice, consumable data, equipment/process notes | Process, consumable and operating limits need to match. |
| Gas/flux, intended parameter source, preheat and interpass constraints | Product data, project requirements, existing procedure notes | Provides job-specific operating values and thermal conditions. |
| PWHT, CVN, seismic, cyclic loading or other special requirements | Contract, design notes, Engineer direction | Additional requirements may change the route or exceed this product's prepared scope. |
What the WPS contains
Delivery includes one complete English WPS draft for the agreed procedure and supported production range, in PDF and editable Word formats. It records the applicable code basis, joint and base-metal details, process sequence, consumables, pass-specific operating variables, temperature requirements, relevant technique controls, and the supported scope and limitations.
First draft within 24 hours after project information and scope are confirmed; included revisions within 24 hours after comments and revision scope are confirmed. Weekends and public holidays are included. For an earlier deadline, tell us in advance and we will confirm whether we can accommodate it.
We prepare it from your project files and confirmed welding data. If a necessary value is missing, we ask you to confirm it. Review the WPS before submission; two original-scope revision rounds requested within 30 calendar days of first delivery are included. See revision and refund terms.
If a prequalified condition does not fit
If a Clause 5 condition does not fit, a valid and applicable PQR may support preparation through the existing-PQR route.
See a complete A36 SMAW WPS demonstration with source-based parameters and an example document download.
Start with the actual project conditions and available records.