CAVOREN WPSAWS D1.1 WPS preparation

Defined repair operation · procedure applicability

When does a defined weld repair need a separate WPS?

A repair WPS question begins with the repair instruction: what defect or area is being removed, what joint will remain after excavation, and what conditions has the responsible project authority approved? Only then can the existing production WPS and supporting qualification be checked against the repair operation.

Working rule: A repair WPS records the defined, approved repair operation using the applicable Clause 5 route or existing PQR support.

First distinguish a weld return from repair of existing work

A planned weld that is removed and rewelded as part of the original production operation can be a return to the original joint detail. A repair to an existing weld or member begins with a condition that has been identified for disposition. That repair may have a different excavation shape, access, restraint, material condition, sequence, or project approval than the original weld.

This guide starts after the responsible project authority has defined the repair operation.

Build the repair input and evidence matrix

Evidence groupRequired recordWPS review question
Repair authorityApproved repair instruction, drawing/sketch and revision; responsible approver; applicable project specification and code editionAre the operation, extent, sequence and applicable limitations explicit?
Excavation resultLocation; length/depth/width/profile; joint members exposed; remaining thickness; access and root/backside condition; verification methodWhat joint geometry will actually be welded after excavation?
Base-metal factsMaterial specifications/grades, thicknesses, product form, heat-treatment or delivery condition, traceability and available MTRsCan those actual materials enter the Clause 5 branch or be supported by the existing PQR?
Existing weld evidenceOriginal WPS and revision; supporting PQR(s), test reports, process/pass records and applicable qualification editionDoes the procedure still cover the repair’s joint, position, material, thickness and actual process conditions?
Repair operationProcess sequence; consumables and sizes; preheat/interpass and any specified thermal controls; access, cleaning, backgouging and pass planAre required WPS fields supported by the code route, PQR and product data?
Inspection and releaseApproved examination/hold points and acceptance documents from the project authorityWhat records must accompany the repair? These are project acceptance instructions, not invented WPS rules.

Compare the repair with the existing procedure

  1. Use the governing code edition and approved repair instruction, preserving document revisions.
  2. Translate the excavation drawing into a weld type and actual joint detail. Do not assume the original CJP/PJP/fillet designation still describes the remaining geometry.
  3. Compare materials, thicknesses, position, process, consumables, backing/backgouging and temperature with the original WPS and qualification basis.
  4. If the original WPS is prequalified, check whether the repair detail and all conditions satisfy the applicable Clause 5 provisions. A new document may be a revision or a separate WPS depending on the controlled document system and project instruction.
  5. If qualification is required, use an applicable existing PQR and its correct test-type and variable path; flag any missing record details.
  6. Write the procedure to the approved scope and supported values, identifying unresolved inputs for the project.

Three outcomes for the review

Evidence resultPreparation outcomeNext evidence needed
Repair conditions fall within the existing supported procedureDocument why the existing WPS applies, or prepare the requested controlled copy/revision if authorized by the project systemRepair instruction, applicable WPS revision, and traceable qualification basis
A procedure document is needed and every field has Clause 5 or PQR supportPrepare a separate repair WPS within that defined operationComplete materials, excavation sketch, approved process conditions and any required PQR records
Repair design or qualification evidence is missing or conflictsHold the affected WPS conclusion; report the precise unknown or mismatchClarification from the responsible project authority, or a qualifying existing PQR. New qualification testing is outside this preparation service.

Example: an excavation changes the joint detail

An original groove weld WPS covers the production joint. A repair instruction then calls for local excavation from one side, and the resulting cavity does not match the original groove preparation. The original WPS name alone does not establish applicability. Compare the actual cavity and welding sequence with the permitted prequalified detail or with a supporting PQR. If the repair sketch does not define enough geometry to make that comparison, request the missing repair instruction before writing production values.

Repair responsibility

Apply Clause 7.25, applicable Clause 11 provisions for existing structures, and project documents to the actual repair. A WPS records welding variables and supported limits; the responsible project parties define and accept the repair.

Code basis and related guides

Basis: AWS D1.1/D1.1M:2025 base edition plus the registered July 28, 2026 base-edition errata; AMD1 is not included. The governing contract edition controls each project.

Need a WPS prepared from defined project inputs?

Provide the drawing, applicable procedure or PQR, and the records that establish the requested production conditions.

Start a WPS request

Continue this WPS review

Start with the defined repair instruction and compare the resulting joint with procedure support.