Temperature review · Table 5.11
How do you find the minimum preheat for a two-member joint?
Identify each member’s Table 5.11 preheat category from its listed material and process condition, use the thickest part at the point of welding for the thickness band, then apply the higher side-specific minimum. Table 5.6 strength groups answer a separate filler-matching question.
A practical workflow for the actual joint
- Confirm identity on both sides. From material certificates or controlled project records, record each ASTM/API specification, grade or class, product form and applicable thickness condition. Do not treat a steel family name or yield strength as a substitute for the listed grade.
- Keep the strength-group check separate. If the WPS is intended to be prequalified, map each member to Table 5.6 and retain any grade, product-form or thickness restriction. Use those Groups I–V for the applicable filler-metal matching check; do not use them to select preheat.
- Determine each Table 5.11 category. Match each member to its listed category and the welding process/electrode condition. For example, GMAW uses the ordinary listed process condition in Categories B or C, depending on the steel entry. A different process or SMAW electrode condition may use another category.
- Measure thickness where the weld is made. Enter the thickest joined member at that point—not the weld size or a thicker remote section. Select the applicable SI or US customary table column and its printed band boundaries.
- Read both minima and govern by the higher one. AWS 5.7.2 applies the highest minimum where the two base metals have different Table 5.11 requirements. Do not average categories or temperatures.
- Apply additional conditions. Check the table notes, initial temperature, any qualifying hydrogen-based category, project minimum, separate maximum interpass limit, material-specific cap and the contract edition before writing the WPS.
The AWS D1.1 preheat calculator compares supported material/process choices on both sides and reports the governing value. It applies SI and US table columns independently. The result does not establish Table 5.6 eligibility or complete WPS qualification; confirm those separately.
Worked example: A572 Grade 50 joined to Grade 60
Consider a GMAW joint between ASTM A572 Grade 50, 12 mm thick, and ASTM A572 Grade 60, 25 mm thick. Assume the stated grades are verified, the contract uses the 2025 base edition, there is no documented reduced-hydrogen route, the starting temperature is at least 0°C, and no project minimum raises the result.
| Member | Table 5.6 strength group | Table 5.11 GMAW category | Minimum at 25 mm |
|---|---|---|---|
| A572 Grade 50, 12 mm | Group II | Category B | 10°C |
| A572 Grade 60, 25 mm | Group III | Category C | 65°C |
The 25 mm Grade 60 member is the thickest part at the point of welding, so use the >20 through 38 mm band for the joint’s Table 5.11 checks. Category B calls for 10°C and Category C calls for 65°C in that band; the higher minimum governs. The Table 5.6 groups (II and III) are recorded separately for the filler matching review. They are not the reason the 65°C preheat applies.
Enter both A572 grades, GMAW, 25 mm and the actual starting temperature in the calculator to reproduce the supported temperature check. The example is bounded to these stated assumptions; it is not a complete WPS or confirmation that all Clause 5 conditions are met.
Details that can change the result
- Material identity: Table 5.11 includes grade-specific entries. For instance, A572 Grade 50 is listed in Category B, while Grades 60 and 65 are in Category C for the stated ordinary process condition. Do not assign a category to an unlisted grade by similarity.
- Process and consumable condition: SMAW with non-low-hydrogen electrodes can follow a different row from low-hydrogen SMAW, SAW, GMAW or FCAW. GMAW-S is not a Clause 5 prequalified process; a preheat calculation alone does not qualify it.
- Hydrogen-based lower categories: Categories D–G require their listed material and process conditions and documented qualifying diffusible-hydrogen evidence at the specified limit. An electrode name or normal handling practice is not that test evidence.
- Initial temperature and project limits: A marked freezing-point cell can invoke a 20°C/70°F minimum when the base metal starts below 0°C/32°F. A project minimum may increase the temperature. A maximum interpass limit is separate and can conflict with the minimum.
- Alternative methods: Annex B and the special Engineer-approved multi-electrode SAW path have their own inputs and conditions. Do not replace Table 5.11 with a carbon-equivalent estimate or assumed reduction.
Basis and scope
This page uses AWS D1.1/D1.1M:2025 base edition plus the registered July 28, 2026 base-edition errata; AMD1 is excluded. Contract-specified editions govern. Relevant provisions are Table 5.6, Table 5.11 and Clauses 5.7 and 7.6, including applicable notes. For an existing-PQR WPS, use its applicable qualification rules and the actual record instead of assuming a new Clause 5 path.
Where and when to verify the temperature
Under 7.6, check temperature before starting each pass and maintain the WPS minimum through the required area. For each member thinner than 1-1/2 in [38 mm], the heated region extends from the welding point in all directions by at least twice that member's thickness. For a member at or above that threshold, the extent is at least its thickness and not less than 3 in [75 mm]. Determine the extent separately on each side when thicknesses differ; the higher required minimum temperature governs the joint.
SI example: joining 20 mm and 50 mm members means checking at least a 40 mm extent on the thinner side and at least 75 mm on the thicker side. This describes the required maintained region, not a universal instruction to place every instrument exactly at its edge. The measurement instruction should identify instrument/method, checked location, pass and time, minimum and any maximum, and the actual observation. Apply any additional project or material measurement requirements.
If the joint cools below the WPS minimum, restore the required temperature before the next pass. If an applicable maximum is exceeded, wait and recheck under the procedure rather than adding another pass. Preserve these observations in the parameter record and connect them to the interpass limits.
Annex B needs a complete method, not just CE or Pcm
- Identify the route and the ordinary Table 5.11/6.10 comparison value; collect steel chemistry with its source, process, joint, single/multipass condition, thicker-member thickness, hydrogen evidence, restraint and service/HAZ requirements.
- Use carbon and the Annex B CE formulation with Figure B.1 to establish the applicable Zone. Zone I uses hydrogen control; Zone II has a limited single-pass fillet hardness-control branch and a hydrogen-control branch; Zone III uses hydrogen control. Hardness control is not a general groove-weld or Q&T method.
- For hydrogen control, establish Pcm, H1/H2/H3 from applicable evidence, susceptibility group, restraint and the Table B.2 thickness row. For hardness control, document the selected hardness basis, applicable Figures B.2–B.4 and process factor; retain graphical-read precision.
- Check the chosen method's limits and footnotes, then record the route-specific qualification basis before using any lower temperature.
For Clause 6, 6.8.4 permits the applicable calculated lower value to be used for qualification; that does not let an existing PQR's recorded minimum be rewritten. For a new Clause 5 WPS, do not automatically replace Table 5.11 with a lower Annex B number when its adoption basis is unresolved. Table B.2's “<” footnote requires qualification testing when both proposed preheat and interpass temperatures are below the indicated table value and below Table 5.11.
The Annex B text formula and Figure B.1/B.2 captions have an unresolved N/Ni discrepancy in the registered base edition. Keep the formula and locator with the calculation, and resolve borderline graph readings rather than silently changing the chemistry. Select the Zone, hydrogen class and restraint as part of the method review.
HPS 70W: keep material rules separate from bridge scope
Where the actual contract is within D1.1 scope, A709 HPS 70W is listed in Table 5.6 Group IV and the applicable low-hydrogen/SAW/GMAW/FCAW branch of Table 5.11 Category C. Select filler from the applicable group and actual classification/product requirements; do not substitute a lower group because the product is described only as “weathering steel.” Check any exposed-unpainted weathering requirement separately.
The HPS 70W maximum preheat/interpass is 400°F [200°C] for thickness at or below 1-1/2 in [40 mm], and 450°F [230°C] above it. The SI maximum-temperature breakpoint is 40 mm, whereas the ordinary Table 5.11 preheat thickness steps include 38 mm: keep them distinct and use each code unit system independently. Derive the minimum from the correct thickness row and compare it with the maximum plus actual project/material requirements.
A bridge contract specifying D1.5 remains outside this D1.1 service, even if it uses the same material grade. For delivery-state and steelmaker thermal evidence, continue to Q&T/TMCP temperature and heat-input review.
Continue this WPS review
Confirm both members, process, thickness, and hydrogen inputs before determining the joint temperature path.
- Preheat calculator
Calculate from confirmed material, process, thickness, and hydrogen inputs.
- Base metal lookup
Check the material designation before using a category.
- Hydrogen evidence guide
Review consumable evidence and handling context.
- Weld parameter record
Record the source and status of proposed temperature values.