Special-process review · Clause 6
ESW / EGW: how can an existing PQR support a production WPS?
For electroslag and electrogas welding, a production WPS depends on specialized PQR details. Reconcile the tested shoe, guide, flux, oscillation, electrical setup and joint geometry before carrying any condition into production.
First confirm the process and the record type
Electroslag welding (ESW), narrow-gap electroslag welding (ESW-NG) and electrogas welding (EGW) use specialized equipment and have their own qualification provisions. Under AWS D1.1/D1.1M:2025 they are not Clause 5 prequalified processes. This review starts only when an applicable, complete PQR and supporting test record already exist. The PQR is compared with the production setup under Table 6.7, with the applicable Table 6.8 checks added when CVN requirements apply.
Identify which process and variant the PQR actually supports; do not treat the term “vertical welding” or a generic process code as enough. The procedure record must preserve the actual machine, shoe, guide, flux, electrode, oscillation and joint details tied to the tested condition.
Specialized production fields to reconcile to the PQR
| Record group | Capture from the PQR and production setup |
|---|---|
| Molding shoes | Metallic or nonmetallic; melting or nonmelting; solid or water-cooled construction; section dimensions and cross-sectional area. |
| Oscillation | Travel speed, stroke, dwell time, and distance from consumable guide to molding shoe. |
| Consumable guide and flux system | Guide metal chemistry and core area; flux system/type and composition; guide coating; flux burden. |
| Electrodes and electrical setup | Number and diameter of electrodes, current, voltage, AC/DC and polarity, constant-current/constant-voltage mode, wire-feed speed and single/multipass method. |
| EGW shielding gas | Gas composition and total flow as actually qualified; preserve the EGW-specific comparison. |
| Joint geometry and temperature | Square-groove root gap or nonsquare-groove cross-sectional area; qualified base-metal thickness and position; preheat/interpass and PWHT conditions. |
| Test support | Applicable PQR test reports and NDT/VT records, plus CVN reports and supplementary-variable support when required. |
Table 6.2 has a process-specific base-metal thickness range of 0.5T–1.1T for ESW/EGW; do not borrow the familiar 2T or unlimited entry from an ordinary CJP process row. The ESW/EGW test set is also specialized: two reduced-section tension tests, one all-weld-metal tension test and four side bends, with the applicable visual/NDT provisions. Check the exact PQR and the table notes before carrying any coverage into a production WPS.
Table 6.7 is a change-trigger table, not a parameter recipe
The following is a compact screening map for changes from the recorded PQR. The strict “greater than” thresholds stay strict; a stated qualitative term such as “significant” must not be replaced by an invented percentage. A trigger identifies the table’s listed route; it does not create a result or authorize this service to perform new testing.
| Change from PQR | Table 6.7 listed path |
|---|---|
| 1. Significant change in weld-metal composition of electrode or consumable guide | WPS test |
| 2. Molding shoe changes between metallic and nonmetallic | RT/UT |
| 3. Shoe changes between melting and nonmelting | RT/UT |
| 4. Any section dimension or area of a solid nonmelting shoe decreases more than 25% | RT/UT |
| 5. Solid nonmelting shoe changes to a water-cooled design, or the reverse | WPS test |
| 6. Oscillation transverse travel speed changes more than 10 in/min [4 mm/s] | RT/UT |
| 7. Oscillation dwell changes more than 2 s, except as necessary to compensate for joint-opening change | RT/UT |
| 8. Oscillation stroke changes guide-to-shoe distance more than 1/8 in [3 mm] | RT/UT |
| 9. Consumable-guide metal core cross-sectional area changes more than 30% | WPS test |
| 10. Flux system changes (for example, cored, magnetic electrode or external) | WPS test |
| 11. Flux composition changes, including guide coating | WPS test |
| 12. Flux burden changes more than 30% | RT/UT |
| 13. Electrode diameter changes more than 1/32 in [1 mm] in either direction | RT/UT |
| 14. Number of electrodes changes | WPS test |
| 15. Current changes more than 20% in either direction | WPS test |
| 16. AC/DC or polarity changes | RT/UT |
| 17. Voltage changes more than 10% in either direction | RT/UT |
| 18. ESW/EGW is combined with another welding process | WPS test |
| 19. Single-pass and multipass methods change | WPS test |
| 20. Constant-current and constant-voltage power-source modes change | RT/UT |
| 21. Wire-feed speed changes more than 40% in either direction | WPS test |
| 22. Travel speed, for an automatic function other than arc-length/deposition-rate control, changes more than 20% in either direction, except as necessary to compensate for joint-opening change | RT/UT |
| 23. EGW only: any gas component changes more than 5% of total flow | WPS test |
| 24. EGW only: total shielding-gas flow changes more than 25% in either direction | RT/UT |
| 25. Vertical position changes more than 10° | RT/UT |
| 26. Nonsquare-groove cross-sectional area increases | WPS test |
| 27. Nonsquare-groove cross-sectional area decreases | RT/UT |
| 28. Joint thickness moves outside 0.5T–1.1T | WPS test |
| 29. Square-groove root gap changes more than 1/4 in [6 mm] in either direction | RT/UT |
| 30. PWHT changes | WPS test |
AWS D1.1/D1.1M:2025 public preview provides edition context but is not a substitute for the complete controlled Table 6.7. The table’s RT/UT path refers to the code’s specified examination provisions (Clause 8 Parts E/F, and Clause 10 Part F where tubular application governs). It does not mean that all entries require a new WPS mechanical test. Confirm the exact table notes and any governing tubular or contract provisions from the controlled code text.
Keep CVN support as a second overlay
If the contract or code requires CVN, complete the applicable Table 6.8 supplementary-variable review in addition to Table 6.7. The specialist row, test thickness and materials, flux/electrode identities, heat input and other supplementary controls must be supported by the PQR and test reports. Table 6.7 clearance alone does not demonstrate CVN qualification.
If a needed Table 6.7 path is WPS testing or the CVN review shows new qualification tests are required, stop the WPS preparation review at that gap. Cavoren’s existing-PQR service prepares a production WPS only from applicable existing evidence; it does not develop ESW/EGW process settings, conduct RT/UT, or arrange new procedure or CVN testing.
Code basis and related guides
AWS D1.1/D1.1M:2025 base edition plus registered errata, excluding AMD1. Primary provisions include 6.8.2, Table 6.2, Table 6.7 and Table 6.8 when CVN applies; use the exact notes and any applicable Clause 10 provisions from the controlled standard.
Send the project drawing, exact consumable or material identification, and complete supporting records where applicable.
Continue this WPS review
Reconcile specialized machine, shoe, guide and joint records with the applicable existing PQR.
- PQR coverage matrix
Keep actual records separate from production limits.
- Supplementary CVN variables
Add the applicable toughness evidence review.
- Base-metal thickness coverage
Keep the specialized ESW/EGW branch distinct.
- Existing-PQR WPS preparation · $499
For a procedure fully supported by applicable existing records; no new qualification testing.